Originally Posted by ChaosSlayer View Post
unless I am wrong Task system has 1 annoying thing - you must do steps in order.
You're wrong.

If all activities have the step column set to zero, they must be completed in order.

If any activity has non-zero step number, than all activities with the same step number can be worked on simultaneously.

See Task 16, Arachnida in the PEQ DB for an example.

I agree with you though, writing tasks by hand can be a pain in the a**e